| Scope of works | Installation of Equipment, Piping and Instrumentation for 600TPD Palm Refinery Plant |
| Location | Pasir Gudang, Johor |
| Year of completion | August 2010 |
| Scope of works | Installation of Equipment, Piping and Instrumentation for 600TPD Palm Refinery Plant |
| Location | Lumut, Perak. |
| Year of completion | August 2007 |
| Scope of works | Proposed Addition Works to Complex Oleochemicals Building
|
| Location | Pasir Gudang, Johor. |
| Year of completion | September 2006 |
| Scope of works | Proposed Fatty Acid Plant 3 c/w Equipment Installation |
| Location | Pasir Gudang, Johor |
| Year of completion | November 2005 |
| Scope of works | Internal Piping Works for Fatty Acid Plant |
| Location | Pasir Gudang, Johor |
| Year of completion | November 2005 |
| Scope of works | Stainless Steel Product Export Pipeline Interchange |
| Location | Kuantan, Pahang |
| Year of completion | September 2004 |
| Scope of works | Installation of Export Pipes |
| Location | Kuantan, Pahang |
| Year of completion | September 2004 |